Project Process

PROJECT CHECKLIST (from Land Acquisition to House Set)

Use this Table to Track Progress on your Project…

Legend: X = Typically responsible; O = optional svc by FW; NA = not applicable

PROCESS Owner FW notes
Step 1 LAND/LOT DEVELOPMENT
Purchase and/or clear title X
Accessible to Modular Carriers & Crane (conduct site accessibility study) X
Perc/Probe Test (or public sewer if available) conduct prior to purchase if not already owned X
Land Surveyed and/or Site Development Plan X O
Step 2 FORMS/PROCEDURES/PERMITS
Select Modular Model, Options OR Full Custom X
Order Preliminary Drawings ($1500 for rancher on crawl space + $250/add’l engineered level) X
Develop and Finalize Prints, Plans, Options, Finishes and Specs X X
Order Permit Sets (aka ‘Working Drawings’ or ‘Sub Sets’) X
Contracts Signed X X
Sign-Off on Plans and Specs X
Secure Financing (process started previously) X
Set Target Occupancy Date X X
Deposit due to release home for production X TBD
Establish Construction Activities/Schedule X
Obtain and Post Permits:
– Building (req’d)
– Electrical (where appl)
– Plumbing (where appl)
– Mechanical (where appl)
– Road/Culvert/Driveway apron
X X subs may pull permit
Application for Gas/Electrical Service (promptness req’d!) X
Site Survey (stake out) X O
Step 3 FOUNDATION & SITEWORK
Order Steel Beams and Columns X
Deliver Dumpster and Port-a-john X
Site Preparation, Lot clearing, Demolition X O
Layout and Excavation X
Form and Pour Footings; footing inspection X
Install Footing Drains, Basement Stone, Under-Slab Utilities (e.g. bathroom rough-in) X
Install Foundation Walls w/ Anchor Clips/Straps X
Apply Foundation Damp-Proofing and Vapor Barrier X
Install Sump Pump Crock and Rough Plumbing X
Install Basement Windows and/or Crawl Space vents X
Install Foundation Drain Tile and Cover X
Prep Opening in Floor for Posts/Support Columns X
Pour Basement Floor and Garage Floor X
Backfill X
Step 4 SITE PREPARATION
Foundation is Square and Level X
Foundation and Footings have passed Inspection X
Obstacles for Crane and Carriers have been Removed X
Access Route & Staging Area for Crane and Carriers are prepared X X
Set Crew and Crane Schedules are Confirmed X
Bulldozer and Operator Scheduled and Confirmed X X
Utility Crews have been Scheduled for Turn-off / Turn-on (if applicable) X
Weather Forecast for Set Day looks Adequate X
Certified Funds/Bank Letter/Wire Confirmed and Available on Delivery Day
X
Step 5 MODULAR HOME SET
Modules Delivered/Received X
Unwrap Modules and Check Inventory of Ship-Loose pieces X
Mark Mating Lines on the Foundation X
Posts/Support Columns and Basement Stairs Set/Installed X
Locate Pick-Points on the Modules, Prepare for Lifting X
Set, Fasten and Check Module X
Prepare Mating Surfaces X
Prepare Wires, Pipes, Ducts and Stairs X
Lift Jointed Roof Sections with Crane X
Set/Fasten Dormers, Gables, Bay Windows, Garage Panels, Fireplace Chimneys, and other exterior Ship-Loose pieces X
Make the Home Weather-Tight and Secure X
Sign Set-Release X
Step 6 HOME FINISHING for our Turnkey customers:
Your “heavy lifting” is done. Now you can relax a bit while FW begins the process of finishing up your home and handing you the keys. X Enjoy!